Excavation work can involve: demolition, asbestos removal, explosives and/or high-risk construction work, but does not include a:
- Mine
- Bore
- Trench used for burial
PCBU specific duties
As a person conducting a business or undertaking (PCBU), you have a duty to manage the risks of excavation work. Other specific duties include:
- Ensuring workers have the relevant high risk work licence before work is commenced
- Ensuring all asbestos that may be disturbed by the excavation work is removed by a competent person.
- Contacting Before You Dig Australia to check locations of electrical cables and other assets. Information on underground essential services must be:
- Made available to workers, principal contractor and subcontractors
- Readily available for inspection
- Kept until the work finishes or for at least 2 years after a notifiable incident.
- Securing the work area from unauthorised access before excavating a trench that is more than 1.5m deep
- Preparing a safe work method statement (SWMS) if the excavation work being carried out:
- Is in or near a shaft or trench that is 1.5 metres deep, or a tunnel
- Where there is a risk of a person falling more than 2 metres, and
- Where there is a risk of mobile powered plant colliding with pedestrians or other powered mobile plant.
For more information on SWMS, please refer to our information sheet. To learn more about how to prepare a SWMS, access the interactive SWMS tool.
For more information
Model Codes of Practice
- Excavation Work
- Construction Work
- How to safely remove asbestos
- How to manage work health and safety risks
- The interactive safe work method statement (SWMS) tool provides information on preparing, using and reviewing SWMS for high risk construction work.
Other resources
- Part 6.3, Division 3 of the Model WHS Regulations
- Guide for tunnelling work
- Safe Work Australia webpage - Excavation